Finance[cashflows] - present value of a list of cash flows
|
Calling Sequence
|
|
cashflows(flows, rate)
|
|
Parameters
|
|
flows
|
-
|
list of cash flows, one per period, starting at period = 1
|
rate
|
-
|
interest rate per period
|
|
|
|
|
Description
|
|
•
|
The function cashflows() computes the present value of a list of cash flows. The flows are given one per period, starting at period 1
|
•
|
This function is part of the finance package.
|
•
|
The command with(Finance,cashflows) allows the use of the abbreviated form of this command.
|
•
|
Since cashflows used to be part of the (now deprecated) finance package, for compatibility with older worksheets, this command can also be called using finance[cashflows]. However, it is recommended that you use the superseding package name, Finance, instead: Finance[cashflows].
|
|
|
Compatibility
|
|
•
|
The Finance[cashflows] command was introduced in Maple 15.
|
|
|
Examples
|
|
I will receive 100 U, 200 U and 50 U at the end of this year, and at the end of the next 2 years. If the discount rate is 10%, this is equivalent to receiving immediately the amount of:
>
|
|
>
|
|
| (1) |
If these cash flows are generated from an initial investment of 95 units, the net present value is
>
|
|
| (2) |
Since the npv is positive, the project would be accepted on that basis.
What is the internal rate of return?
>
|
|
| (3) |
>
|
|
| (4) |
The internal return is 115%. Since this is bigger than the discount rate the project would be also be accepted on the IRR basis. One can see the npv versus rate by plotting
>
|
|
It is prudent to do this plotting, since it is possible to have multiple solutions to the IRR relationship (npv=0).
|
|